29. Provisions

MEUR

Provision for refund claim Provision for litigation claim Other provisions Total
Total provision at the end of the period 31 December 2015

4.6 2.2 0.0 6.8
Increases

0.2 0.0 0.5 0.7
Provisions used

-0.5 -2.0 0.0 -2.5
Reversals

-0.1 0.0 0.0 -0.1
Total provision at the end of the period 31 December 2016

4.2 0.2 0.5 4.9



MEUR



31 Dec 2016 31 Dec 2015
Non-current provisions



3.0 5.2
Current provisions



1.9 1.5
Total



4.9 6.8







The provision for refund claim includes guarantees related to new construction business and the 10-year warranty period after the completion of the work. The provision for refund claim is measured on the basis of claims presented and an assessment based on prior experience. The provision for refund claim will be used, if applicable, within ten years from the reporting date.

The provision for litigation claim relates to a litigation process initiated during 2008, concerning one of SATO's development projects in Helsinki. Based on Helsinki Court of Appeals decision given on 30 January 2015, the expense was recognised in the consolidated income statement of 2015.